Applying Requirements Management with Use Casesby Roger Oberg, Leslee Probasco and Maria Ericsson ©Copyright 1999 by Rational Software Corporation. All Rights Reserved. Technical Paper TP505 (Version 1.3)If you are new to or somewhat familiar with requirements management and are interested in requirements process improvement, this paper offers a framework with which to develop your own approach
Software and System Development in the Age of ProcessFor most software and system development teams, the 1990s have been process-intensive when compared to the more freewheeling days of the past. Standards for measuring and certifying effective software development process have been introduced and popularized. Many books and articles on software development process and related material on business process modeling and re-engineering have been published. Increasing numbers of software tools have helped define and apply effective software development process. The global economys dependence on software accelerated in the decade, enabling development processes and improving system quality. So how do we explain the high incidence of the software project failure today? Why are many, if not most, software projects still plagued by delays, budget overruns, and quality problems? How can we improve the quality of the systems we build as our businesses, national economies, and daily activities become increasingly dependent on them? The answers, as always, lie in the people, tools, and processes applied to our profession. Requirements management is often proposed as a solution to the ongoing problems of software development, yet relatively little attention has been focused on improving the practice of this discipline. This paper presents the elements of an effective requirements management process and highlights some of the obstacles to its successful implementation. Requirements management applies equally to software-only projects and to projects in which software is only a part of the end result or not included at all. For convenience, the paper will hereafter use the term "system" to mean any or all of these things. However, it is the abstract nature of software development, alone or in combination with hardware that complicates requirements management, and is therefore the primary focus of the paper. Why Manage Requirements?Simply put, system development teams who manage requirements do so because they want their projects to succeed. Meeting their projects requirements defines success. Failing to manage requirements decreases the probability of meeting these objectives. Recent evidence is supportive:
Avoiding failure should be sufficient motivation to manage requirements. Increasing the probability of a successful project and other benefits of managing requirements may be equally motivational. The Standish Groups CHAOS report further established that managing requirements well was the factor most related to successful projects. What is a Requirement?The first step towards understanding requirements management is to agree on a common vocabulary. Rational defines a requirement as "a condition or capability to which the system [being built] must conform." The Institute of Electronics and Electrical Engineers uses a similar definition. Well-known requirements engineering authors Merlin Dorfman and Richard H. Thayer offer a compatible and more refined definition that is specific but not necessarily limited to software: "A software requirement can be defined as:
What is Requirements Management?Since requirements are things to which the system being built must conform, and conformance to some set of requirements defines the success or failure of projects, it makes sense to find out what the requirements are, write them down, organize them, and track them in the event they change. Stated another way, Requirements Management is:
This definition is similar to Dorfman and Thayers and the IEEEs "Software Requirements Engineering." Requirements Engineering includes elicitation, analysis, specification, verification, and management. All of these activities are incorporated in the definition of requirements management presented here and taught by Rational Software. The difference lies mainly in the choice of the word "management" rather than "engineering." Management is a more appropriate description of all the activities involved, and it accurately emphasizes the importance of tracking changes to maintain agreements between stakeholders and the project team. For those unfamiliar with the term "elicitation," it is defined as the set of activities that teams employ to elicit or discover stakeholder requests, determine the real needs behind the requests and a suitable set of requirements that might be placed on the system to meet those needs. The Problems of Requirements ManagementSo what might be difficult about a process intended to ensure that a system conforms to the expectations set for it? When put into practice on real projects, difficulties come to light. Figure 1 displays the results of a 1996 survey of developers, managers, and quality assurance personnel. It shows the percentage of respondents who experienced the most frequently mentioned requirements-related problems. Figure 1. A more comprehensive list of problems includes:
When these problems are combined with inadequate requirements management and process skills, and the lack of easy-to-use tools, many teams despair of ever managing requirements well. Rational Software has developed the expertise to instruct teams in requirements management skills and process. In addition, Rational Requisite®Pro is an accessible tool for automating effective requirements management. Requirements Management SkillsTo resolve the problems mentioned above, Rational encourages the development of key skills. These skills are presented below in what appears to be sequential order, but in an effective requirements management process they are applied continuously in varied order. Here they are presented in the sequence one would likely apply to the first iteration of a new project. Figure 2. Key Skill 1: Analyze the ProblemProblem analysis is conducted to understand business problems, target initial stakeholder needs, and propose high-level solutions. These acts of reasoning and analysis find "the problem behind the problem." During problem analysis, agreement is gained on a statement of the real problems and the stakeholders are identified. Initial solution boundaries and constraints are defined from both technical and business perspectives. If appropriate, the business case for the project analyzes return on investment that is expected from the system. Key Skill 2: Understand Stakeholder NeedsRequirements have many sources. They may come from anyone with an interest in the
outcome of the project. Customers, partners, It is important to know how to determine who the sources should be, how to get access to those sources, and how to elicit information from them. The individuals who serve as primary sources for this information are referred to as "stakeholders" in the project. If you are developing an information system to be used internally within your company, you may include people with end-user experience and business domain expertise in your development team. Very often you will start the discussions at a business-model level rather than at a system level. If you are developing a product to be sold to a marketplace, you may make extensive use of your marketing people to better understand the needs of customers in that market. Techniques for eliciting requirements include interviews, brainstorming, conceptual prototyping, questionnaires, and competitive analysis. The result of requirements elicitation is a list of requests or needs that are described textually and graphically, and that have been given priority relative to one another. Key Skill 3: Define the SystemTo define the system means to translate and organize the understanding of stakeholder needs into a meaningful description of the system to be built. Early in system definition, decisions are made on what constitutes a requirement, documentation format, language formality, degree of requirements, request priority and estimated effort, technical and management risks, and scope. Part of this activity may include early prototypes and design models directly related to the most important stakeholder requests. We use the word "description" rather than "document" to avoid the perceived limitation inherent in the common use of the latter. A description may be a written document, electronic file, a picture, or any other representation meant to communicate system requirements short of the system itself. The outcome of system definition is a description of the system that is both natural language and graphical. Some suggested formats for the description are provided in later sections.
Key Skill 4: Manage the Scope of the SystemThe scope of a project is defined by the set of requirements allocated to it. Managing project scope to fit the available resources (time, people, and money) is key to managing successful projects. Managing scope is a continuous activity that requires iterative or incremental development, which breaks project scope into smaller more manageable pieces. Using requirement attributes, such as priority, effort, and risk, as the basis for negotiating the inclusion of a requirement is a particularly useful technique for managing scope. Focusing on the attributes rather than the requirements themselves helps desensitize negotiations that are otherwise contentious. It is also helpful for team leaders to be trained in negotiation skills and for the project to have a champion in the organization, as well as on the customer side. Product/project champions should have the organizational power to refuse scope changes beyond the available resources or to expand resources to accommodate additional scope. Key Skill 5: Refine the System DefinitionWith an agreed-upon high-level system definition and a fairly well understood initial scope, it is both possible and economical to invest resources in more refined system definitions. Refining the system definition includes two key considerations: developing more detailed descriptions of the high-level system definition, and verifying that the system will comply with stakeholder needs and behave as described. The descriptions are often the critical reference materials for project teams. Descriptions are best done with the audience in mind. A common mistake is to represent what is complex to build with a complex definition, particularly when the audience may be unable or unwilling to invest the critical thinking necessary to gain agreement. This leads to difficulties in explaining the purpose of the system to people both inside and outside the project team. Instead, you may discover the need to produce different kinds of descriptions for different audiences. This paper includes suggested formats for detailed natural language, formal text, and graphical descriptions. Once the description format is established, refinement continues throughout the project lifecycle. Key Skill 6: Manage Changing RequirementsNo matter how carefully you define your requirements, they will change. In fact, some requirement change is desirable! It means that your team is engaging your stakeholders. Accommodating changing requirements is a measure of your teams stakeholder sensitivity and operational flexibility team attributes that contribute to successful projects. Change is not the enemy, unmanaged change is. Figure 3. A changed requirement means that more or less time has to be spent on implementing a particular feature, and a change to one requirement may have an impact on other requirements. Managing requirement change includes activities such as establishing a baseline, keeping track of the history of each requirement, determining which dependencies are important to trace, establishing traceable relationships between related items, and maintaining version control. As Figure 3 illustrates, it is also important to establish a change control or approval process, requiring all proposed changes to be reviewed by designated team members. Sometimes this single channel of change control is called a Change Control Board (CCB). Important Requirements ConceptsTo apply requirements management skills to a project, certain requirements management concepts are useful for everyone on the project to understand. They include:
Requirement TypesThe larger and more intricate the system, the more types of requirements appear. A requirement type is simply a class of requirements. By identifying types of requirements, teams can organize large numbers of requirements into meaningful and more manageable groups. Establishing different types of requirements in a project helps team members classify requests for changes and communicate more clearly. Usually, one type of requirement can be broken down, or decomposed, into other types. Business rules and vision statements can be types of high-level requirements from which teams derive user needs, features, and product requirement types. Use cases and other forms of modeling drive design requirements that can be decomposed to software requirements and represented in analysis & design models. Test requirements are derived from the software requirements and decompose to specific test procedures. When there are hundreds, thousands, or even tens of thousands of instances of requirements in a given project, classifying requirements into types makes the project more manageable. Cross-Functional TeamsUnlike other processes, such as testing or application modeling, which can be managed within a single business group, requirements management should involve everyone who can contribute their expertise to the development process. It should include people who represent the customer and the business expectations. Development managers, product managers, analysts, systems engineers, and even customers should participate. Requirements teams should also include those who create the system solution engineers, architects, designers, programmers, technical writers, and other technical contributors. Testers and other QA personnel should be counted as important team members. Figure 4. Often, the responsibility for authoring and maintaining a requirement type can be allocated by functional area, further contributing to better large project management. The cross-functional nature of requirements management is one of the more challenging aspects of the discipline. TraceabilityAs implied in the description of requirement types, no single expression of a requirement stands alone. Stakeholder requests are related to the product features proposed to meet them. Product features are related to individual requirements that specify the features in terms of functional and non-functional behavior. Test cases are related to the requirements they verify and validate. Requirements may be dependent on other requirements or they may be mutually exclusive. In order for teams to determine the impact of changes and feel confident that the system conforms to expectations, these traceability relationships must be understood, documented, and maintained. While traceability is one of the most difficult concepts to implement in requirements management, it is essential to accommodating change. Establishing clear requirement types and incorporating cross-functional participation can make traceability easier to implement and maintain. For more information on different strategies for requirements traceability, see the white paper, "Traceability Strategies for Managing Requirements with Use Cases" [6]. Figure 5. Multi-Dimensional AttributesEach type of requirement has attributes, and each individual requirement has different attribute values. For example, requirements may be assigned priorities, identified by source and rationale, delegated to specific sub-teams within a functional area, given a degree-of-difficulty designation, or associated with a particular iteration of the system. To illustrate, Figure 6 displays attributes for a Feature Requirement Type from a Learning Project in Rational RequisitePro requirements management tool. As implied by the title of the screen, the requirement type and attributes for each type are defined for the entire project, ensuring usage consistency across the team. Figure 6. In Figure 7, instances of feature requirements are displayed for a specific project in RequisitePro. Note that even without displaying the entire text for each requirement, we can learn a great deal about each requirement from its attribute values. In this case, its priority and difficulty no doubt assigned by different members of the team will help the team begin to scope the project to available resources and time, taking into account both stakeholder priorities and a very rough estimate of effort reflected in the difficulty attribute value. In more detailed types of requirements, the priority and effort attributes may have more specific values (e.g., estimated time, lines of code, etc.) with which to further refine scope. This multi-dimensional aspect of a requirement, compounded by different types of requirements each with its own attributes is essential to organizing large numbers of requirements and to managing the overall scope of the project. Figure 7. Change HistoryBoth individual requirements and a collection of requirements have histories that become meaningful over time. Change is inevitable and desirable to keep pace with a changing environment and evolving technology. Recording the versions of project requirements enables team leaders to capture the reasons for changing the project, such as a new system release. Understanding that a collection of requirements may be associated with a particular version of software allows you to manage change incrementally, reducing risk and improving the probability of meeting milestones. As individual requirements evolve, it is important to understand their history: what changed, why, when, and even by whose authorization. Putting Requirements Management to WorkRequirements management employs the key skills and concepts presented above to identify and resolve the problems successfully. To build a system that truly meets customers needs, the project team must first define the problem to be solved by the system. Next, the team must identify stakeholders from whom business and user needs are elicited, described, and prioritized. From this set of high-level expectations or needs, a set of product or system features should be agreed upon. Detailed software requirements should be written in such a form as can be understood by both the customers and the development team. We have found that using the language of the customer to describe these software requirements is most effective in gaining the understanding and agreement. These detailed software requirements are then used as input for the system design specifications as well as for test plans and procedures needed for implementation and validation. Software requirements should also drive the initial user documentation planning and design. Figure 8. To facilitate this, the project team should:
These essential requirements management activities are independent of industry, development methodology, or requirements tools. They are also flexible, enabling effective requirements management in the most rigorous and the most rapid application development environments.
Requirements Management: Workflow DetailsRequirements management can follow an infinite number of domain-specific paths. The following approach prescribes six detailed workflows that apply to each of the key requirements management skills but can be applied to any domain. The following workflow diagrams are from the Rational Unified Process, Requirements Workflow Details. These workflows are expressed in terms of workers, activities and artifacts (input or output). The accompanying text in this paper describes each workflow detail briefly, in the hopes of stimulating your thoughts and interest in improving your requirements management process. More information on the Rational Unified Process can be found at www.rational.com. Workflow Detail: Analyze the ProblemIn Problem Analysis, the primary activity is to develop the vision for the project. Output from this activity is a vision document that identifies the high-level user or customer view of the system to be built. The vision expresses initial requirements as key features the system must possess in order to solve the most critical problems and meet key stakeholder needs. The system analyst has the primary role in this workflow. The system analyst should have problem domain expertise and an understanding of the problem, and should be able to describe a process that he or she believes will solve the problem. Active involvement from various project stakeholders is required and all relevant stakeholder requests should be considered. To begin the Manage Dependencies activity, features should be assigned attributes such as rationale, relative value or priority, and source of request. As the vision develops, the analyst identifies users and systems (the actors) of possible use cases. Actors are the first element of the use-case model, which will define the systems functional and non-functional technical requirements. Figure 9. Workflow Detail: Analyze the ProblemInitiation: One or more stakeholders who perceive a problem will initiate the workflow. A system analyst in a development team may facilitate a session to help the initial stakeholders describe the problem they want solved. It is important to gain agreement on a concise statement of the perceived problem. Key elements of a problem statement are shown in the following table:
The problem statement succinctly explains the purpose of the project. Problem analysis stimulates further investigation into all stakeholder requests and the initial business case including compelling benefits and roughly estimated costs. In parallel with defining problem statements, the team should also compile a glossary by keeping track of commonly used terms and agreeing on their definitions.
Problem analysis also identifies the main system actors. Actors are users of the system or any other system that will exchange information with it. At this stage, problem analysis should briefly identify some obvious ways that the actors will interact with the system. Descriptions should be oriented towards business process rather than system behavior. For example, a budgeting program may allow one type of actor to "Create departmental budget," while another actor will be able to "Consolidate departmental budgets." The system analyst may later break them into additional use cases that align more meaningfully with specific system behavior. For example, "Create departmental budget" could result in system use cases such as "Import spreadsheet information" and "Create budget views." The problem analysis session described above is often performed more than once, maybe with different stakeholders, and intermingled with internal development team sessions. The system analyst who conducted the meeting with the stakeholders will lead a session with members of the development team to envision a technical solution to the problems, derive features from the initial stakeholder inputs, and draft the vision description, the first definition of the system to be built. To facilitate understanding of the proposed solution among the initial stakeholders, the system analyst may use modeling tools or manual drawing techniques to complement the vision description. The initiating stakeholders are consulted at multiple points to help refine the problem description and constrain the number and scope of possible solutions. Stakeholders and system analysts manage dependencies in this workflow by negotiating the priority of key features and gaining a general understanding of the resources and effort needed to develop them. While priority and effort/resource estimates inevitably change, managing dependencies early establishes an important pattern that continues throughout the development lifecycle. It is the essence of the scope management and an early predictor of project success. After several drafts, the vision reaches a point at which the team must decide whether to invest in additional requirements elicitation. By the same time, the business case approval process has been initiated separately. Although not addressed further in this paper, the business case describes:
Workflow Detail: Understand Stakeholder NeedsIf the initial problem analysis justifies additional investment, the Understanding Stakeholder Needs workflow begins in earnest. The key activity is eliciting stakeholder requests. The primary outputs are collections of prioritized stakeholder needs and features, which enable refinement of the vision document, as well as a better understanding of the requirements attributes. Also, during this workflow you may start discussing the system in terms of its use cases and actors. Another important output is an updated glossary of terms to facilitate common vocabulary among team members. Figure 10. Workflow Detail: Understand Stakeholder NeedsThe system analyst and key stakeholders identify additional stakeholders, elicit their requests and determine key needs and features via interviews, workshops, storyboards, business process use cases, and other techniques. One or more system analysts facilitate these sessions. These requirement workshops are among the most useful elicitation techniques. The process includes users, help-desk personnel, business owners, testers, and others who have a stake in the outcome of the proposed project. Stakeholder requests are often ambiguous, overlapping, and even extraneous. In addition to formal elicitation results, stakeholder requests may be expressed in well-formatted documents, defect and enhancement requests from databases, or e-mail and groupware threads. System analysts record, categorize, and prioritize the identified key stakeholder needs.
Based on a better understanding of stakeholder needs, the system analysts in the development team refine the vision document, paying special attention to developing a "product position statement". In two or three sentences, this statement establishes the compelling value of the project. The statement should include intended users, the problems it solves, the benefits it delivers, and the competitors it replaces. All team members should understand this project theme. System analysts also update the glossary to facilitate common understanding of terms. Key stakeholders are consulted at multiple points to negotiate priorities of new features derived from understanding stakeholder needs and gain a current understanding of resources and effort needed to develop them. As with problem analysis, managing dependencies in this workflow helps manage scope. It also establishes traceability between stakeholder requests, needs and system features, so stakeholders can be sure their inputs were considered. Workflow Detail: Define the SystemThe first two Requirements workflow details, Analyze the Problem and Understand Stakeholder Needs, create early iterations of key system definitions, including features specified in the vision document, a first outline to the use-case model, and initial requirement attributes. The next workflow detail, Define the System, completes the description of the high-level system requirements with refinement of the feature definitions, the addition of new actors, use cases, and supplementary specifications. Figure 11. Workflow Detail: Define the SystemThe glossary is updated to reflect current understanding about the terms used to describe features and the requirements captured in the use-case model and the Supplementary Specifications. The system analyst uses the feature set defined in the refined vision to derive and describe the use cases that elaborate the users' view of the systems expected behavior. The use-case model serves as a contract between the customer, the users, and the system developers on how the selected features will function in the system. It helps set realistic expectations and goals for system developers and helps customers and users to validate that the system will meet these expectations. Some system requirements do not fit well in use cases. The system analyst describes these in a supplementary specification. Many non-functional requirements, such as usability, reliability, performance, and supportability requirements often end up here. It should be noted that many non-functional requirements of these types are specific to a single use case. It is better for use case specifiers to place these requirements in the use case specification itself (see the Refining the System workflow), leaving the supplementary specification for system-wide non-functional requirements. In this workflow detail, the system analyst creates and sets attributes for the supplementary requirements (such as priority and related use cases). In addition, the system analyst adds and updates attribute values for the initial and new use cases. Finally, the system analyst manages dependencies by tracing important user needs and critical features to related use cases and requirements described in supplementary specifications. Workflow Detail: Manage the Scope of the SystemAfter identifying feature-level requirements, describing most actors, use cases, and other requirements specified in the supplementary specifications, the system analyst should gather and assign values as accurately as possible to requirement attributes such as priority, effort, cost, and risk. This allows a better understanding of how to determine the initial scope of the system release and can also enable the architect to identify the architecturally significant use cases. The iteration plan, developed in parallel by project and development management, first appears in this workflow detail: Manage the Scope of the System. Also known as a development plan, the iteration plan defines the number and frequency of iterations planned for the release. The highest risk elements within scope should be planned for early iterations. Other important outputs from the Managing Scope workflow include the initial iteration of the software architecture document and a revised vision that reflects analysts and key stakeholders increased understanding of system functionality and project resources. Like the business case, mentioned earlier, and first issue of the iteration plan, the software architecture document is not an artifact of requirements management workflows, although it is related and is part of the Rational Unified Process. It is not the subject of this paper.
Figure 12. Workflow Detail: Manage the Scope of the SystemArchitects prioritize use cases for their risk coverage, architectural significance, and architectural coverage. While the system may be defined with many use-case and supplementary specification requirements, only a subset of use cases are usually critical to good system architecture. With prioritized use cases, architects refine the iteration or development plan and model a use-case view of the system architecture in tools such as Rational Rose. System analysts manage dependencies by refining requirement attributes for features in the vision. They also refine requirements in use cases and supplementary specifications. System analysts ensure that appropriate traceability* exists for stakeholder needs, features, use-case requirements, and supplementary specification requirements. The term "appropriate traceability" is deliberate. See the inset text on Traceability later in this paper. This step is among the most important in the entire project. For the first time the breadth of knowledge about the proposed system is available to make serious commitments on requirements, project resources and delivery dates. At the same time, it must be understood that these requirements will change as the depth of knowledge increases. If dependencies have been managed in the previous three workflows, this step is much easier, and future changes will be easier. Throughout the life of the project, as situations and environments change, this workflow detail is revisited many times as system analysts must negotiate revised project scope and vision with key stakeholders. Managing the scope of the project to match available resources is successful only if stakeholders and development team members view this step as a natural progression not an ambush on users expectations or an attempt to blackmail the organization for more time and money. This workflow will need to be repeated at major milestones in the project to assess whether new insight into the system and its problems requires change to the scope. While committed requirements, budgets, and deadlines are hard to change, an in-depth understanding of prioritized use cases, supplementary specifications, and early system iterations inevitably lead to scope reconsideration. Once again, it is critical that the project team engages in habitual scope management before reaching the refinement stage, as well as throughout the project lifecycle as changes occur. Representative stakeholders must understand and trust that their priorities and interests are taken seriously during increasingly difficult scope negotiations. By the time system requirements are refined, only important requirements remain to be negotiated or modified. Unless effective scope management habits have been established, your project may be doomed as a "death march" a hopelessly over-scoped project moving inexorably towards delays and cost overruns. Workflow Detail: Refine the System DefinitionMoving forward to Refine the System Definition, this workflow detail assumes that system-level use cases have been outlined and actors have been described, at least briefly. Through managing the project scope, the features in the vision have been re-prioritized and are now believed to be achievable by fairly firm budgets and dates. The output of this workflow is a more in-depth understanding of system functionality expressed in detailed use cases, revised supplementary specifications, and early iterations of the system itself. Obviously, not all systems will have user interfaces and not all early iterations will include GUI elements. We use them here only as an example of an early iteration. Other examples includes prototypes, models, and storyboards. Figure 13. Workflow Detail: Refine the System DefinitionThe use-case specifier details the definition of the flow of events, pre- and post-conditions, and other textual properties of each use case. To minimize the effort and enhance readability, it is advisable to use a standard document format or a use case specification template, to capture textual information about each use case. Creating well-thought-out use case specifications is critical to the quality of the system. This specification development requires a thorough understanding of the stakeholder needs and features related to the use case. It is desirable to have several members of the project team (such as software engineers) participate in creating the use cases. In parallel, the use case specifier revises the supplementary specification with additional requirements that are not specific to the use case. The user-interface designer models and prototypes the user interface of the system. This work is highly correlated to the evolution of the use cases. The use-case specifier and the system analyst revise the effort, cost, risk, and other attribute values for each requirement that is understood better. The results of this system definition refinement are submitted to another round of the Managing Scope workflow detail. Once you know more about the system, you may want to change the priorities. Most definitely, the scope of the system release will need to be reviewed and refined, if necessary. Workflow Detail: Manage Changing RequirementsAs changes occur -- and they inevitably will -- the Manage Changing Requirements workflow detail needs to be applied continuously throughout the life of the project, as discussed for the Manage the Scope of the System workflow detail. The output of this workflow can cause modification to every artifact, which in turn requires effective communication among all project team members and stakeholders. In this workflow we introduce additional artifacts that are affected by the requirements workflows. Changes to requirements naturally affect the system models that are represented in the analysis & design workflows. Requirement changes also affect tests created to validate the proper implementation of the requirements. As in earlier examples, these artifacts are part of the Rational Unified Process but are not the subjects of this paper. Traceability relationships identified in the process of managing dependencies are keys to understanding these impacts.
Another important concept to Manage Changing Requirements is requirement history tracking. By capturing the nature and rationale of requirements changes, reviewers (anyone on the software project team whose work is affected by the change) receive the information needed to respond to the change properly. Figure 14. Workflow Details: Manage Changing RequirementsRequests for changes to requirements may be initiated by any stakeholder or project team member for many various reasons. All Change Requests (Cr.'s) including changes to requirements or enhancement requests, as well as defects, should all be channeled through the same Change Request Management (CRM) process. At a minimum, this should include logging and tracking the request in a centralized database system and should enforce review by a central review authority. See other sections of the Rational Unified Process for more details of such a CRM process. The system analyst should coordinate the review activity, preferably by a CCB (Change Control Board), collecting and reviewing all change requests, and classify them as:
Once classified, the proposed changes to requirements are assigned attributes and values as described in other requirements workflows. In reviewing change requests, the system analyst presents proposed prioritized requirement changes to a CCB comprised of representative stakeholders and project team members. Scope modifications that exceed resources should be rejected or elevated to stakeholder representatives that are empowered to approve required changes to date and budget commitments. The CCB approves or rejects changes to requirements. The system analyst communicates requirements changes to requirements specifiers or makes changes directly to requirements in the vision, use cases, supplementary specification documents or other requirements artifacts. The requirements reviewers (developers, testers, managers, and other project team members) evaluate the impact of changes to requirements on their work by reviewing requirement history. Finally, they implement the change and make appropriate changes to related requirements for which they have authority. SummaryThe need to manage requirements is not new. So, what makes the preceding information worth considering now? First, if your projects are not regularly satisfying customers, meeting deadlines, and staying within budget, you have reason to reconsider your development approach. If in doing so, you determine that requirements-related problems are undermining your development efforts, you have reason to consider better requirements-management practices. Second, the requirements management practices summarized in this paper embody the collective experience of thousands, and are the well-considered opinions of a number of individuals who have spent years working with customers in the field of requirements management. We suggest that this overview of their contributions -- and the more thorough presentation of them made in Rationals Unified Process -- represent a "best practice" in requirements management. You will not find more proven advice on requirements anywhere. The authors would like to acknowledge the direct and indirect contributions of Dr. Ivar Jacobson, and those of Dean Leffingwell, Dr. Alan Davis, Ed Yourdon, and Elemer Magaziner. Most importantly, we appreciate the Rational Software customers who have applied and improved these practices in hundreds of development projects. Finally, in the past two years Rational Software, a leader in the business of producing effective software development solutions, has taken on the challenge of requirements management and emerged with the tools to automate this difficult task. The chronic, pervasive problems of requirements management are solvable. And that, ultimately, may be the best reason to start practicing excellence in requirements management today. References
|
|