Operation Materials
Flows are used to model the consumption and production of material from buffers.
Different types of flows exist:
flow_start:
Flows that consume (or produce) material at the start of an operationplan.
The quantity consumed or produced is proportional to the quantity of the
operationplan.
flow_end:
Flows that produce (or consume) material at the end of an operationplan.
The quantity consumed or produced is proportional to the quantity of the
operationplan.
flow_fixed_start:
Flows that consume (or produce) material at the start of an operationplan.
The quantity consumed or produced is constant and independent of the
quantity of the operationplan.
flow_fixed_end:
Flows that produce (or consume) material at the end of an operationplan.
The quantity consumed or produced is constant and independent of the
quantity of the operationplan.
Fields
Field |
Type |
Description |
buffer |
buffer |
Buffer from which material will be moved or transferred
into.
This is a required field.
|
operation |
operation |
Operation to which the material flow is associated.
This is a required field.
|
quantity |
double |
Material quantity being consumed or produced per unit of
the operationplan. |
effective_start |
dateTime |
Date after which the material consumption is valid.
Before this date the planned quantity is always 0.
|
effective_end |
dateTime |
Date at which the material consumption becomes invalid.
After this date (and also at the exact date) the planned
quantity is always 0.
|
priority |
integer |
Priority of the flow, used in case of alternate flows.
The default is 1.
Lower numbers indicate more preferred flows.
|
name |
non-empty string |
Optional name of the flow.
All flows with the same name are considered to be
alternates of each other.
|
search |
string |
Defines the order of preference among the alternate flows.
The valid choices are:
PRIORITY
Select the alternate with the lowest priority number.
This is the default.
MINCOST
Select the alternate which gives the lowest cost.
The cost includes the cost of all upstream operations,
resources and buffers.
MINPENALTY
Select the alternate which gives the lowest penalty.
The penalty includes the penalty of all penalties
incurred in the upstream plan along the flow.
MINCOSTPENALTY
Select the alternate which gives the lowest sum of
the cost and penalty.
The sum is computed for the complete upstream path.
|