An operation represents an activity: these consume and produce material, take time and also require capacity.
An operation consumes and produces material, modeled through flows.
An operation requires capacity, modeled through loads.
Different operation types exist:
Fields
Field | Type | Description |
---|---|---|
name | non-empty string | Unique name of the operation.
This is the key field and a required attribute.
|
item | item | Reference to the item being produced.
If left unspecified we will try to determine the item
as the producing records from the operation-material
records: if an operation has only a single operation-material
with a positive quantity then we use its item as the
item of the operation.
|
location | location | Location of the operation.
Default is null.
The working hours and holidays for the operation are
taken from the ‘available’ calendar of the location.
|
effective_start | dateTime | Date when the operation becomes valid. |
effective_end | dateTime | Date when the operation becomes valid. |
priority | integer | Priority of this operation to produce the specified item.
This is useful when there are multiple operations
producing the same item-location, or the same item-location
can also be replenished with purchase orders
and/or distribution orders.
|
description | string | Free format description. |
category | string | Free format category. |
subcategory | string | Free format subcategory. |
fence | duration | Time window from the current date of the plan during
which all operationplans are expected to be
frozen/released.
When the ‘FENCE’ constraint is enabled in the solver, it
won’t create any new operation plans in this time fence.
Only the externally supplied and locked operationplans will
then exist in this time window.
|
size_minimum | positive double | A minimum quantity for operationplans.
The default value is 1.
A request for a lower, non-zero quantity will be rounded up.
|
size_minimum_calendar | calendar | A calendar to define the minimum size of operationplans
when this value varies over time. The end date of the
operationplan determines which date we use as lookup in the
calendar.
If both the size_minimum and size_minimum_calendar are
specified, we use the highest value.
|
size_multiple | positive double | A lotsize quantity for operationplans. |
size_maximum | positive double | The maximum quantity for operationplans.
Note that this value limits the size of individual
operationplans. The solver can create multiple operationplans
of this maximum size, so this value does NOT constrain the
total planned quantity on the operation. The field is
useful to break big operationplans in smaller ones.
|
cost | double | The cost of executing this operation, per unit of the
operation_plan.
Depending on what the operation models, this
represents transportation costs, manufacturing costs,
procurement costs, delivery costs, etc...
The raw material cost and the resource usage cost are added
to this cost and should not be included in this value.
The default value is 0.
|
posttime | duration | A post-operation time, used as a buffer for uncertain
capacity or operation duration.
The solver will try to respect this time as a soft
constraint. Ie when required to meet demand on time the
post-operation time can be violated.
Resources are not loaded during the post-operation time.
This field is used to model time-based safety stock
targets, aka days of inventory. It is then set for the
producing operation of a certain buffer.
If you want to model a safety stock quantity, you can use
the minimum or minimum_calendar fields on the buffer.
|
detectproblems | boolean | Set this field to false to skip problem detection on
this operation.
The default value is true.
|
loads | list of load | A list of all resources loaded by this operation. |
flows | list of flow | A list of all buffers where material is consumed from or produced into. |
level | integer | Indication of how upstream/downstream this entity is
situated in the supply chain.
Lower numbers indicate the entity is close to the end
item, while a high number will be shown for components
nested deep in a bill of material.
The field is export-only.
|
cluster | integer | The network of entities can be partitioned in completely
independent parts. This field gives the index for the
partition this entity belongs to.
The field is export-only.
|
hidden | boolean | Marks entities that are considered hidden and are normally not shown to the end user. |
Models an operation with a fixed duration regardless of the quantity. E.g. a transport operation.
This is the default operation type.
Field | Type | Description |
---|---|---|
duration | duration | Duration of the operation.
The default value is 0.
|
Models an operation where the duration changes linear with the quantity. E.g. a production operation.
The total duration of the operation plan is the sum of:
Field | Type | Description |
---|---|---|
duration | duration | Fixed component of the duration of the operationplan.
The default value is 0.
|
duration_per | duration | Variable component of the duration of the operationplan.
The default value is 0.
|
Models a choice between different operations. It has a list of alternate sub-operations listed, each with a priority.
Operation minimum, multiple and maximum size constraints of each individual alternate sub-operation are respected. The ones on the operation_alternate operation itself are ignored.
Field | Type | Description |
---|---|---|
search | string | Defines the order of preference among the alternate loads. The valid choices are:
|
suboperations | List of suboperation | List of alternate sub-operations.
See Suboperations
|
This operation type plans the demand proportionally over a number of operations. It has a list of alternate sub-operations listed, each with a percentage.
The percentages are treated as a hard constraint by the solver. This means that if one of the alternates can’t deliver the requested quantity, the complete split operation is considered as infeasible. (If we’ld treat it as a soft constraint, we would distribute the infeasible quantity among the other alternates).
Minimum, multiple and maximum size constraints on the sub-operations are respected. This means that we can end up with a split that deviates to some extent from the specified percentages.
The percentages don’t need to add up to 100%. We use the relative ratio’s of the sub-operations.
Field | Type | Description |
---|---|---|
suboperations | List of suboperation | List of sub-operations to divide the plan across.
See Suboperations
|
Models a sequence a number of ‘step’ sub-operations, to be executed sequentially.
Field | Type | Description |
---|---|---|