Resources

Resources represent capacity. They represent a machine, a worker or a group of workers, or some logical limits.

Operations will consume capacity using loads.

Different types of resources exist:

  • A default resource is constrained with a maximum load size. The resource size defines how many operations that can use the resource in parallel.
    For detailed planning and scheduling this is the most suitable resource type.
    E.g. A resource that can run 2 jobs at the same time.
  • A bucketized resource is constrained with a maximum load quantity per time bucket.
    For master planning and rough cut capacity planning this is most suitable resource type.
    E.g. A resource that can produce 1000 units per week.
  • An infinite resource has no capacity limit.

Fields

Field Type Description
name non-empty string
Unique name of the resource.
This is the key field and a required attribute.
description string Free format description.
category string Free format category.
subcategory string Free format subcategory.
owner resource
Resources can be organized in a hierarchical tree.
This field defines the parent resource.
When an operation loads a resource which has members, the planning algorithm will select one of the child resource.
members list of resource
Resources can be organized in a hierarchical tree.
This field defines a list of child resources.
location location
Location of the resource.
Default is null.
The working hours and holidays for the resource are taken from the ‘available’ calendar of the location.
maximum double
Defines the maximum size of the resource.
The default value is 1, i.e. a resource that can handle 1 operationplan at a time (provided of course that this operationplan requires 1 unit on the resource).
A problem is reported when the resource load exceeds than this limit.
This field is ignored on resource of type buckets and infinite.
maximum_calendar calendar
Refers to a calendar storing the available capacity.
Use this field when the resource size is varying over time. If this field is populated, the field maximum is ignored.
On resources of type buckets this calendar defines the time buckets as well as the maximum quantity per time bucket.
This field is ignored on resources of type infinite.
cost double
The cost of using 1 unit of this resource for 1 hour.
The default value is 0.
detectproblems boolean
Set this field to false to suppress problem detection on this resource.
Default is true.
maxearly duration
Time window before the ask date where we look for available capacity.
The default value is 100 days.
loads list of load Defines the capacity of the operations.
loadplans list of loadplan
This field is populated during an export with the plan results for this resource. It shows the resource load profile.
The field is export-only.
The description of the loadplan model is included in the section on operationplan.
level integer
Indication of how upstream/downstream this entity is situated in the supply chain.
Lower numbers indicate the entity is close to the end item, while a high number will be shown for components nested deep in a bill of material.
The field is export-only.
cluster integer
The network of entities can be partitioned in completely independent parts. This field gives the index for the partition this entity belongs to.
The field is export-only.
setup non-empty string The name of the current setup of the resource, ie the setup of the resource at the start of the planning horizon.
setupmatrix setupmatrix The name of the setup matrix which specifies the changeover times between setups.
hidden boolean Marks entities that are considered hidden and are normally not shown to the end user.

Resource_default

A default resource is constrained with a maximum load size. The resource size defines how many operations that can use the resource in parallel.

For detailed planning and scheduling this is the most suitable resource type. E.g. A resource that can run 2 jobs at the same time.

No fields are defined in addition to the ones listed above.

Resource_buckets

A bucketized resource is constrained with a maximum load quantity per time bucket.

For master planning and rough cut capacity planning this is most suitable resource type. E.g. A resource that can produce 1000 units per week

No fields are defined in addition to the ones listed above, but the maximum_calendar field must is be specified.

Resource_infinite

An infinite resource has no capacity limit. It is useful to monitor the loading or usage of a resource without constraining the plan.

The fields ‘maximum’ and ‘maximum_calendar’ are unused for this resource type.