Suboperations

Suboperations apply to operations of type operation_routing, operation_alternate, operation_split.

Each of these refer to child-operations.

Field Type Description
operation operation Sub-operation.
owner operation Parent operation.
priority integer
For alternate operations: Priority of this alternate.
For routing operations: Sequence number of the step.
For split operations: Proportion of the demand planned along this suboperation.
Lower numbers indicate higher priority.
When the priority is equal to 0, this alternate is considered unavailable and it can’t be used for planning.
Default value is 1.
effective_start dateTime Earliest allowed start date for using this suboperation.
effective_end dateTime Latest allowed end date for using this suboperation.