Suboperations apply to operations of type operation_routing, operation_alternate, operation_split.
Each of these refer to child-operations.
Field | Type | Description |
---|---|---|
operation | operation | Sub-operation. |
owner | operation | Parent operation. |
priority | integer | For alternate operations: Priority of this alternate.
For routing operations: Sequence number of the step.
For split operations: Proportion of the demand planned
along this suboperation.
Lower numbers indicate higher priority.
When the priority is equal to 0, this alternate is
considered unavailable and it can’t be used for planning.
Default value is 1.
|
effective_start | dateTime | Earliest allowed start date for using this suboperation. |
effective_end | dateTime | Latest allowed end date for using this suboperation. |