The report shows the details of all operations planned. It displays their start date, end date and quantity.
Field | Description |
---|---|
Operationplan | Identifier of this operation instance. |
Operation | Name of the operation. |
Quantity | Quantity of the operationplan. |
Start date | Start date of the operationplan. |
End date | End date of the operationplan.
Note that in case of unavailable time, the difference between the start and
end date can be bigger than the specified duration of the operation. For
instance, if the weekends are modelled as unavailable time, an operation
with a duration of 1 day can start on friday 7AM and end on monday 7AM.
|
Criticality | Indication of the urgency of the operationplan.
A criticality of 0 indicates that the operationplan is on the critical
path of one or more demands.
Higher criticality values indicate a delay of the operationplan will
not immediately impact the delivery of any demand.
A criticality of 999 indicates an operationplan that isn’t used at all to
meet any demand.
|
Status | Status of the operationplan:
|
Unavailable | Total unavailable time over the duration of the operationplan.
Continuing on the above example, the unavailable time would be 2 days.
|
Owner | In case of nested operationplans this field shows the identifier of the owning operationplan. This applies to alternate operations and to routing operations. |